A quarterly report on the status of Alexandria’s capital projects is headed to the City Council tomorrow (Tuesday) with some bad news: the pandemic has created some setbacks and additional challenges for anticipated projects across the city.
At the Potomac Yard Metro station, a contractor out of Pennsylvania was unable to make progress on the work for part of the summer due to COVID-19 restrictions
“Work on the AC Switchgear building slowed while WMATA and the Contractor discussed quality concerns with the concrete placement for the east and south walls,” the report said. “The Constructor submitted a notice of a potential delay based on a subcontractor being required to return to Pennsylvania — COVID 19 restrictions.”
Since then, construction has continued on various parts of the station, like the platform foundations, elevator pits, and the A/C Switchgear building.
“WMATA finalized the Change Order to add the South Pavilion to the Contractor’s contract,” the report said. “This action continued past the initial completion timeframe as a result of extended WMATA review time.”
The Waterfront Plan now faces a year of potential funding delays as a result of the pandemic.
“All FY21 funding has been deferred to FY22 due to COVID-19 economic impact,” staff said in the report. “Additional changes were submitted to spread the funding over FY21-FY23 based on when the funding will be needed. As project design optimization and estimations continue, more accurate project costs can be provided.”
Plans for four miles of a transitway corridor along Van Dorn and Beauregard streets were hit with a delay this summer, but has made progress since. The procurement process for the project was delayed due to COVID and phase 2 of the project, an extension up to Southern Towers, was placed on hold following a change of ownership of Southern Towers. Meetings between staff and the new owners have since been scheduled.
Two stream restoration projects also could be impacted by the pandemic: the Strawberry Run stream restoration and Taylor Run stream restoration. Recently, Taylor Run completed the design review and is moving into public engagement, but the report noted that COVID impacts mean the project schedule is subject to change — and to allow additional time for public feedback. Strawberry Run’s estimated completion date has likewise been delayed due to COVID and to allow additional time for feedback.
Some final planned improvements for Windmill Hill Park were in jeopardy over the summer, the report said. The city added a living shoreline and other improvements to the Old Town park to combat debris issues, but a planned Phase II — including a northern pier at the site — had its funding pulled away due to the city’s budget crisis. Since then, the project has been added to the procurement plan for the third quarter of this fiscal year and an updated timeline is imminent.
For the long-troubled King Street Metrorail improvements, the project is likely to require additional funding despite earlier estimations that added costs would still fall within the contingency budget.
The Contractor will continue working towards the completion of Phase I – Reopening of the Bus Loop and overall project completion. Staff will continue to monitor and track the construction progress, working closely with the Contractor’s leadership to advance the project to completion. Additional funding needs resulting from the prolonged construction duration (extension of the CMI services contract) and to cover the cost of unforeseen site and design issues (beyond the existing construction contingency) to be addressed by Staff.
Staff photo by James Cullum
Recent Stories

Are you seeking a confidential space where you can explore your emotions, overcome challenges, and find inner peace? Look no further than our dedicated psychotherapy service! We understand that life can be overwhelming at times, and we’re here to support you every step of the way.
At Peaceful Mind Solutions, our passion lies in helping individuals like you navigate life’s complexities and find the strength to thrive. Our skilled and compassionate therapist is committed to creating a warm, non-judgmental environment where you can express your thoughts and feelings openly. With our personalized approach, we tailor each session to address your unique needs and empower you to overcome obstacles.
Through evidence-based techniques and a deep understanding of the human mind, our therapist will guide you on a transformative journey of self-discovery. Whether you’re dealing with anxiety, depression, relationship issues, or simply seeking personal growth, we’re here to provide guidance and practical tools for lasting change.
Time flies when you’re having fun! The T.C. Williams High School Class of 1973 will hold its 50th reunion July 21-23, 2023 in Alexandria. All graduates and their adult nears and dears are welcome. Events include a Friday evening icebreaker, Saturday dinner dance, and a Sunday brunch. For more information: tcwilliams73.com, 770.789.3534.
Spring Fling at Rising Sol Yoga School
Join us for a day of FREE hot yoga. Experience our class styles and meet our teachers. Buy a bite at the Bake Sale to benefit The Carpenter’s Shelter, peruse some special vendors, take advantage of in-person only discounts on