Post Content

Waterfront Plan and Other Capital Projects Around Alexandria Delayed by COVID-19

A quarterly report on the status of Alexandria’s capital projects is headed to the City Council tomorrow (Tuesday) with some bad news: the pandemic has created some setbacks and additional challenges for anticipated projects across the city.

At the Potomac Yard Metro station, a contractor out of Pennsylvania was unable to make progress on the work for part of the summer due to COVID-19 restrictions

“Work on the AC Switchgear building slowed while WMATA and the Contractor discussed quality concerns with the concrete placement for the east and south walls,” the report said. “The Constructor submitted a notice of a potential delay based on a subcontractor being required to return to Pennsylvania — COVID 19 restrictions.”

Since then, construction has continued on various parts of the station, like the platform foundations, elevator pits, and the A/C Switchgear building.

“WMATA finalized the Change Order to add the South Pavilion to the Contractor’s contract,” the report said. “This action continued past the initial completion timeframe as a result of extended WMATA review time.”

The Waterfront Plan now faces a year of potential funding delays as a result of the pandemic.

“All FY21 funding has been deferred to FY22 due to COVID-19 economic impact,” staff said in the report. “Additional changes were submitted to spread the funding over FY21-FY23 based on when the funding will be needed. As project design optimization and estimations continue, more accurate project costs can be provided.”

Plans for four miles of a transitway corridor along Van Dorn and Beauregard streets were hit with a delay this summer, but has made progress since. The procurement process for the project was delayed due to COVID and phase 2 of the project, an extension up to Southern Towers, was placed on hold following a change of ownership of Southern Towers. Meetings between staff and the new owners have since been scheduled.

Two stream restoration projects also could be impacted by the pandemic: the Strawberry Run stream restoration and Taylor Run stream restoration. Recently, Taylor Run completed the design review and is moving into public engagement, but the report noted that COVID impacts mean the project schedule is subject to change — and to allow additional time for public feedback. Strawberry Run’s estimated completion date has likewise been delayed due to COVID and to allow additional time for feedback.

Some final planned improvements for Windmill Hill Park were in jeopardy over the summer, the report said. The city added a living shoreline and other improvements to the Old Town park to combat debris issues, but a planned Phase II — including a northern pier at the site — had its funding pulled away due to the city’s budget crisis. Since then, the project has been added to the procurement plan for the third quarter of this fiscal year and an updated timeline is imminent.

For the long-troubled King Street Metrorail improvements, the project is likely to require additional funding despite earlier estimations that added costs would still fall within the contingency budget.

The Contractor will continue working towards the completion of Phase I – Reopening of the Bus Loop and overall project completion. Staff will continue to monitor and track the construction progress, working closely with the Contractor’s leadership to advance the project to completion. Additional funding needs resulting from the prolonged construction duration (extension of the CMI services contract) and to cover the cost of unforeseen site and design issues (beyond the existing construction contingency) to be addressed by Staff.

Staff photo by James Cullum

Recent Stories

It was another busy week in Alexandria. This week’s top stories focused on development projects all over the city, from Old Town North to Carlyle and in the West End….

All of Bishop Ireton High School skipped classes today for a good cause. More than 700 students, teachers and administrators participated in a cleanup of 30 sites in and around…

The Truist bank at 2809 Mount Vernon Avenue is temporarily closed today (Friday) after an alleged altercation with a former employee. A former employee who had been terminated allegedly told…

Just Listed includes a 6 BD/4.5 BA home with 10ft ceilings, a gas fireplace and a private balcony.

The Alexandria Branch of the NAACP, Shiloh Baptist Church, and The Departmental Progressive Club present the following two Primary Candidate Forums for the City of Alexandria Virginia. The events are free of charge and open to the public.

Mayoral Forum

● Who: Candidates for Mayor in the City of Alexandria, VA

Read More

Submit your own Community Post here.

Unlike our competitors, Well-Paid Maids doesn’t clean your home with harsh chemicals. Instead, we handpick cleaning products rated “safest” by the Environmental Working Group, the leading rating organization regarding product safety.

The reason is threefold.

First, using safe cleaning products ensures toxic chemicals won’t leak into waterways or harm wildlife if disposed of improperly.

Read More

Submit your own Community Post here.

Pro Coro Alexandria – To the Sea

Join Pro Coro Alexandria, the chamber choir of the Alexandria Choral Society, this Saturday for our concert, “To the Sea.” Experience a variety of songs from beloved choral classics like “Shenandoah” and “What Shall We Do With A Drunken Sailor?”

Del Ray Kitchen Confidential Design Tour

Please join us for Del Ray Kitchen Confidential – a walking tour of recently renovated kitchens in Del Ray with the experts who make the magic happen! FA Design Build owner Rob Menefee and Design Consultant Melissa Fielding walk us

×

Subscribe to our mailing list