Alexandria, VA

The new bus loop — a centerpiece of the King Street-Old Town Metro Access Improvement Project — was scheduled to open in March, but the city now says completion is still four to six months away.

“While delays have continued, we can provide an updated estimate for completion of the phase 1 bus loop,” Lydia Durand, a management analyst with the Department of Project Implementation, told ALXnow. “At this time, we anticipate an approximately four-six month time frame for reopening the bus loop. This accounts for construction of the bus loop, restoration of utilities, intersection signalization, and integration into the DASH, WMATA and City traffic operations systems.”

In 2012, the City Council approved a safer and larger transit area outside the Metro station, with better pedestrian-crossings through the bus loop. The project has been in-progress since November 2018 when the bus loop was closed, but has faced significant delays.

According to the city website, full completion of the project is now scheduled for Spring 2021.

“This project has experienced delays,” Durand said. “Staff continues to actively manage the contractor’s progress on this project and is taking all steps within our contractual rights to hold the contractor accountable for completion of this project in a productive and timely manner.”

Durand said cost increases for inspection and construction oversight could happen, but that they are anticipated to fall within the contingency funding allocated for the project budget.

×

Subscribe to our mailing list