Project to run power lines under Four Mile Run could begin this summer

A rendering of what the view over Four Mile Run will look like after the power lines are undergrounded (via Dominion Energy)

project scheduled to begin this summer will tunnel under the Four Mile Run near the Route 1 bridge to move overhead power lines underground.

As part of the project, Dominion Energy will rebuild its Glebe Substation next year, modernizing the facility that was built in the 1970s and is reaching the end of its service life. The substation serves parts of Arlington and Alexandria.

The project comes after Dominion Energy has promised to invest millions in the area after years of frequent and sometimes devastating power outages.

“Everything will look a lot cleaner, a lot of the equipment will be a lot smaller,” said Ann Gordon Mickel, Dominion Energy’s communication and community lead for the project.

A virtual community meeting will be held tonight (Wednesday) at 6:30 p.m. to discuss the status of the project and what to expect during and after construction.

When work begins, a 250-foot by 250-foot area will be fenced off in the Potomac Yard shopping center parking lot in Alexandria to allow for a 40- to 50-foot deep pit for tunneling.

In Arlington, a pit will be constructed at the substation and there may be temporary intermittent closures on S. Eads Street, as well as on nearby sidewalks and pedestrian paths. Electric service will not be affected.

The underground line will run between the substation and the Potomac Yard Transition Station, which will be decommissioned at the end of the project. The rebuilt Glebe Substation will incorporate new technology, requiring less maintenance and making it more reliable, the power company said.

“Any time you address aging infrastructure and replace it with new technology the reliability always enhances,” said Greg Mathey, a manager of electric transmission communications for Dominion Energy. “The transmission system feeds the distribution system, so the more reliable and hardened we can make the transmission system, the better the distribution system can perform.”

The construction to convert to underground lines is scheduled to continue through 2024. The whole project should be completed by late 2025.

A chart showing the timeline for the Glebe Electric Transmission project (via Dominion Energy)

The entire project is expected to cost about $122.8 million. The State Corporation Commission, which regulates utilities in Virginia, approved the project in 2019. It was originally scheduled to be up and running by this month, but due to the nature of the construction, the timeline was pushed back.

Using a trenchless microtunneling method will increase costs by about $16 million — but it shortens the construction timeline, according to project documents.

This type of tunneling will also reduce construction-related impacts to the Potomac Yard shopping center, as it won’t require as much space for pipes above ground.

The overhead lines that can be seen over Four Mile Run will be removed at the end of the project.

Recent Stories

This past week saw 44 homes sold in Alexandria. The least expensive condo, single-family home or townhouse sale over the past seven days was $200,000 while the most expensive was…

Big changes are coming to Village Brauhaus at 710 King Street in Old Town. The new owners will close the doors of the restaurant for three weeks starting Tuesday, June…

In not so long from now At a local Birchmere Don McLean will be performing live… Musician Don McLean is celebrating the 50th anniversary of his hit song American Pie with…

(Updated 1:35 p.m.) A man was robbed at gunpoint yesterday morning in the area of E. Braddock Road and Commonwealth Avenue in Del Ray. The victim called police from his…

Are you seeking a confidential space where you can explore your emotions, overcome challenges, and find inner peace? Look no further than our dedicated psychotherapy service! We understand that life can be overwhelming at times, and we’re here to support you every step of the way.

At Peaceful Mind Solutions, our passion lies in helping individuals like you navigate life’s complexities and find the strength to thrive. Our skilled and compassionate therapist is committed to creating a warm, non-judgmental environment where you can express your thoughts and feelings openly. With our personalized approach, we tailor each session to address your unique needs and empower you to overcome obstacles.

Through evidence-based techniques and a deep understanding of the human mind, our therapist will guide you on a transformative journey of self-discovery. Whether you’re dealing with anxiety, depression, relationship issues, or simply seeking personal growth, we’re here to provide guidance and practical tools for lasting change.

Read More

Submit your own Community Post here.

Time flies when you’re having fun! The T.C. Williams High School Class of 1973 will hold its 50th reunion July 21-23, 2023 in Alexandria. All graduates and their adult nears and dears are welcome. Events include a Friday evening icebreaker, Saturday dinner dance, and a Sunday brunch. For more information: tcwilliams73.com, 770.789.3534.

Submit your own Community Post here.

×

Subscribe to our mailing list