Taylor Run stream in pretty bad shape, but the City of Alexandria wants to revitalize it into a healthy stream rich with native vegetation.
“It’s in the design phase right now,” said Jesse Maines, division chief for Stormwater Management. Maines estimated the design was about halfway completed, but the department is still reaching out to local stakeholders and continuing internal discussions about the eventual design.
The stream starts near T.C. Williams High School and the Chinquapin Recreation Center, then runs parallel to King Street, eventually emptying into Cameron Run.
Maines said the stream has seen severe erosion over the years as new development has funneled ever-increasing amounts of stormwater through the ravine. There are places where the stream’s banks are a nearly 90-degree drop-off. Restoration of the stream will also help improve water quality to meet the Chesapeake Bay cleanup mandates, the city said on its website.
“We’re considering different kinds of techniques,” Maines said. “This isn’t your grandfather’s stream restoration. The main focus back in the day was just stabilizing everything, but now we [use] natural channel techniques. We want to use those techniques that allow vegetation to be established and hold the banks in.”
The new stream restoration efforts aim to make those banks gradual with native vegetation that slows the water and creates ecological stability. As a bonus, a slower stream with native vegetation could also help return more wildlife to the stream, starting with local macroinvertebrates — bugs, for the less scientifically inclined among us — that dwell in calmer pools of water.
Maines said the design for the project is estimated to be completed sometime around spring or summer this year, followed by a few months of paperwork and procurement, with construction activity starting late this year or the beginning of 2021. Once construction starts, Maines says it’s estimated to take about a year to complete.
After the work gets underway, Maines says the biggest impact the community is likely to see is more truck traffic along King Street near the high school. Construction hours are currently scheduled to be 7 a.m.-5 p.m. during the week, though that could change to 9 a.m. to minimize the impact of truck traffic on buses and other school traffic.
The total cost of the project is currently projected at $4.5 million, though this doesn’t include other features that could be incorporated during the design process. That funding is evenly split between a grant from the Virginia Department of Environmental Quality and matching funding from the city.
The City of Alexandria is scheduled to host a meeting discussing the Taylor Run Stream Restoration project next Thursday (Jan. 16) from 7:30-8:30 p.m. at Douglas MacArthur Elementary School. The meeting will include presentations from the Dept. of Project Implementation and Dept. Transportation and Environmental Services, the city said in a press release, with both departments available to field questions from the public.
Photos via City of Alexandria
Recent Stories

Unwrap the magic of Black Friday and Small Business Saturday all weekend at Current Boutique! Dive into luxury with exclusive deals on pre-loved designer treasures, celebrating sustainable fashion with every purchase. Whether in-store or online, indulge in guilt-free glamour and support local businesses. ✨🛍️👗
💥 Sale: 25% off everything & 50% off tall boots
📅 Date: Friday November 24 – Sunday November 26
Christmas Through The Ages
Christmas Through The Ages – Join the Washington Men’s Camerata, and Guest Director Scott Tucker for a program of Christmas and holiday music spanning the centuries through today, featuring the music of Bach, Lauridsen, Abbie Betinis, and many others.